The Warren County Sheriff’s Office’s new home at Sugar Maple Square is inching closer to completion, with the department now expecting to get its certificate-of-occupancy for a portion of the building this fall and the county continuing to source equipment needed for the transition.
“We should be hopefully able to get certificate-of-occupancy sometime early November,” Sheriff Brett Hightower told the Daily News Thursday.
Fiscal court magistrates on Thursday approved the purchase of nearly a half-million dollars of shelving and communications equipment that will outfit the department’s new evidence room and communications center.
The Sugar Maple strip mall was purchased by the county in 2021 for $1.4 million. Last December, the county accepted a roughly $104,000 bid from Bowling Green-based DRF (Design, Realize and Furnish) Architects who provided design and engineering work for a remodel of the building.
Locally-based Sunbelt Construction, Inc. is handling the $2,289,051 project.
Phase one, the part of Sugar Maple that is closer to completion, will house the department’s criminal investigations division (CID), a training facility, a gym and the expanded evidence room. Patrol deputies will also work out of this side of the building.
Speaking on the expanded evidence room, Hightower said it will provide a much-needed increase in space for the department’s ever-increasing evidence storage needs.
“Right now, it’s probably 20 (feet) by 15 (feet),” Hightower said about the current evidence room. He estimates the new room will measure around 60 feet by 50 feet.
The room will feature collapsible shelving, which the sheriff said will help maximize space in the nearly 3,000 square-foot evidence space. He said this is needed due to the breadth of evidence the department brings in, from firearms used in crimes to lost property.
A separate room for firearms used in criminal activities will be available, and a ventilated room will cut down on odors from seized items, like marijuana.
“It’s just like when you imagine your own home and having closet space and attic space to store and manage, it’s easier to find things and retrieve things,” Hightower said.
WCSO’s CID has already moved into Sugar Maple and others working out of this part of the building will move there in November. Outfitting for phase two likely won’t start until November as well, but Hightower expects it will move a bit faster.
This is the portion that will contain the department’s communications center, along with the business office and Hightower’s office. He said the new communications center will be a more “efficient space,” although the department’s dispatch staff could increase if needed.
“We probably won’t transition the business office down there till kind of near the end of our tax season,” Hightower said, adding that tax invoices this time will still have the department’s current address printed on them.
Hightower summed up his office’s feelings about the upcoming move.
“We’re just excited,” he said.