FRANKLIN — Companies looking to locate data centers in Kentucky have met with resistance at various locations, and Franklin proved no exception Tuesday night.
At a special called meeting of the Franklin Planning and Zoning Commission, the five-member board unanimously voted against amending the text of its zoning regulations that would have expanded the use of heavy industrial-zoned land for data centers.
The text of the proposed amendment, sent to the zoning board for its consideration after a vote by the Franklin City Commission, would have placed advanced technology centers and integrated energy systems to support a center’s energy needs in the group of permitted uses for land zoned for heavy industry in Franklin.
The vote, at the end of a contentious meeting that attracted more than 150 people and lasted nearly four hours, was met with cheers from most of those who gathered at the Franklin Police Department meeting room.
Each of the zoning board members expressed concerns ahead of their respective votes about the language of the proposed amendment, saying that the wording of it offered little in the way of oversight from local government over a proposed data center that would likely handle large amounts of data from artificial intelligence and cloud computing.
“I feel that this language in this particular text amendment is too vague,” board chair Debbie Thornton said. “There are not levers for government to be able to pull, we need far more oversight than this particular text amendment offers.”
The site proposed for the potential center sits on 200 acres of land situated by Exit 2 of Interstate 65 in the far southern end of the city, with plans calling for three facilities of 250,000-300,000 square feet to be built at a $2.1 billion investment, with the construction process ramping up over three years and the expectation of 40-50 full-time jobs.
Along with the board members, several community members and elected officials attending the meeting spoke out against the proposed center, echoing concerns voiced by a contingent of people who protested with signs outside the police department building prior to the meeting.
Franklin resident Jasmine Butt obtained more than 1,200 signatures on a petition started on change.org to oppose the data center.
The petition noted concerns about energy consumption at data centers potentially affecting utility costs in the community, questions about the environmental and noise impact from the natural gas turbines that would power the three data center facilities proposed for the site, concerns about whether the facility would access local water to cool its systems and a dearth of permanent jobs after construction is completed.
“We have a lot of local businesses who already have a hard enough time day in and day out to make ends meet, so if they have higher property taxes and rent increases, soon enough those local small businesses are affected and they cease to exist,” Butt said before Tuesday’s meeting. “This is one of those things that our voices should be loud enough for them to understand that we don’t want this.”
Similar data center projects have met with resistance in Meade County and in Oldham County, where Western Hospitality Partners withdrew an application to build a facility there in July.
Butt and others handed attendees a sheet of paper highlighting some of the issues that have arisen in other communities where large data centers have been built, including tax exemptions and related incentives from the state that attract the companies at the expense of foregone revenue that would otherwise go to public services.
Attorney Tim Crocker, representing the interests that are considering building a data center in Franklin, called a number of witnesses to address those concerns, while raising the possibility during his opening statement of economic benefits for the community with a data center.
“This is going to result in tremendous, generation-changing money four our schools, for our ambulance service, four our county, four our city, for our extension agent and for our library,” Crocker said. “We’re going to get to do some things that nobody dreamed we were ever going to do, build new schools, replace aging sewers and expand fire protection.”
Ford Graham, a South-Carolina based site selector who worked in the selection of Franklin as the location for this potential center, said that one facility at the proposed center could bring in $17 million of local revenue, and that a closed-loop cooling system would be used for the computer chips in use at the facility, meaning that the center would not draw from local water sources.
Other witnesses with backgrounds in engineering and power generation said that the noise produced by the gas turbines that would be constructed to power the proposed center compared favorably to the noise produced by traffic on I-65.
Simpson County Judge-Executive Mason Barnes was one of several elected officials who spoke against the text amendment, saying that a data center, if ultimately approved, should be subject to more specific local regulations that could be incorporated into a conditional use permit.
“Once a conditional use permit is issued, conditions are tied to that permit, you have to abide by this, this and this,” Barnes said. “We need to set the guidelines on what we want and expect to happen in our community.”