Work is set to begin on the intersection of Lehman Avenue and Covington Street after Bowling Green City commissioners on Thursday gave the go-ahead for some minor improvements that will ease traffic flow through the intersection.
Improvements will focus primarily on one corner of the intersection. Drivers turning right from Lehman have to turn on a hairpin corner before accessing Covington. Officials described the project as a “spot-improvement.”
“It’s sharper than a 90-degree turn,” City Manager Jeff Meisel said.
A city memo states that work will involve a small amount of paving along with new curb and gutter placement and modifications to existing storm drainage utilities. Grade work and striping will also be done.
Temporary easements will be granted since some impacts will be made to an adjacent property, the memo states. The city hopes to begin the bidding process for the project within the next month.
New police precinct
Commissioners also chose to pursue a $3.1 million loan that will allow financing for the upcoming Bowling Green Police Department precinct that will be off of Scottsville Road.
Officials OK’d the purchase of the building at 940 Bryant Way last month. The site was the home of Sherwood’s Guns and will provide a space for BGPD to place personnel to cut down on response times.
“If something happens and you’ve got a crew coming down Scottsville Road, you might as well get a helicopter,” Police Chief Michael Delaney said previously. “It’s hard getting out Scottsville Road, even with lights and sirens.”
According to a city memo, the loan will come to the city tax-exempt over ten years at an interest rate of 4.11%. The loan was secured with Pinnacle Financial Partners.
Brent Childers, Neighborhood and Community Services head, presented the purchase to commissioners previously.
He said Thursday that the loan method was chosen to allow the city to use saved funds on construction needs.
“Since this is an acquisition of an existing property, an asset we would hold for a long time, we felt like it was the best financial decision to seek a bank loan,” he said.
The city is also seeking grant funding from the Kentucky Transportation Cabinet to offset costs associated with the sinkhole that appeared recently on Grinstead Way.
City officials learned about the sinkhole last week and crews from Scott & Ritter were out last week doing mitigation work. No threats to any homes in the area are anticipated.
Estimates for repair costs stand now at $250,000, which includes excavation, utility management and repair to the roadway. The grant application to KYTC totals to $100,000, and carries no match requirement.
The city believes that the sinkhole could contain multiple passages for water to flow through that all lead to one underground feature.
“It may be a big sinkhole all tied into one karst feature,” Public Works head Andy Souza told commissioners, adding that crews are excavating now down to roughly 30 feet.
Commissioners will meet again April 21.