An updated timeline for the completion of the long-awaited turf soccer fields at the Lovers Lane Soccer Complex is unknown as work continues to get the fields ready, nearly two years after money was allocated for the fields.
“We want to make sure this project is done correctly, and (is) something that our that our citizens will be able to use for a long time coming,” Bowling Green Parks and Recreation head Brent Belcher said.
Two million dollars were appropriated in the City of Bowling Green’s FY2025 budget for turf fields. Commissioners in November 2024 initially approved a a $70,286 contract with Lexington-based GRW Engineers, Inc. to complete engineering work related to the fields.
After the fields were approved in summer 2024, plans called for the fields to be installed and ready to use between May and August of 2025. However, this deadline was missed after delays with design work.
A combination of flooding at the complex that spring, the opening of a 30-foot deep sinkhole and the volume of work needed for design were all other factors that pushed the timeline back. At that time the city hoped to have the fields installed by fall 2025.
That timeline has again been pushed back.
Belcher said the fields are delayed as work continues to determine soil stabilization and drainage needs.
“Anytime you have a turf project, it’s also a drainage project.” he said. “You have to have drainage for turf because the rain still comes and you still (have to) get rid of the water.”
He said the soil stabilization refers to calculating what grading is needed for the ground the fields will go on, which impacts drainage.
Due to the ongoing work, Belcher said a new completion date is not known yet.
“We’ll have a revised timeline … but there’s just no way I can give (an) idea of what we’re looking at on a completion date yet,” he said. “But, we’re working towards that goal.”
Another $2 million is listed in the city’s FY2026 budget for two turf fields at Preston Miller Park. Belcher said design work is ongoing with those fields, and the hope is to have a vendor for them secured in the near future.
Turf fields promise to cut down on maintenance costs while extending usability of the fields. When the contract was approved, the fields consisted of Bermuda grass, which has a short growing time and must regrow before they can be used again.
With turf, City Manager Jeff Meisel said then, “it’s 365 (days), 12 months of play, year-round.” If maintained properly, turf fields can last up to 10 years before needing replacement.