Riverfront Park is steadily moving closer to reality as city commissioners on Tuesday approved a bid from Scott, Murphy and Daniel to act as a construction manager for phase two of the park.
Phase two was presented to city officials earlier this year with a video from MKSK, the design firm for the Riverfront Park project, showcasing the amenities included.
It will occupy roughly one acre and will sit at the back of the main 71-acre lot that will house the park. A play area consists of a large, flower-shaped area and nearby is a “plinth,” consisting of two levels that feature slides and other play areas.
The whole playground is designed to have a cave theme, with cave formation features dotting the area.
“This is where the park really comes to life,” city Neighborhood Services Director Brent Childers told the Daily News previously. ” … We really wanted to push the envelope for a whole new feature of play, a whole destination, where there’s nothing like any of this anywhere in this part of the world.”
Ordinarily the city follows a standard process for building new facilities. Design work starts the process, followed by a bidding phase.
Once a bid is awarded, the bidder completes construction of the facility. This is how phase one of the park, which includes a new boat ramp, event lawn and podium and rock gardens/trails, is being built.
A construction manager is different. It is broken into two parts, and part one involves “pre-construction.” This will see Scott, Murphy and Daniel “sit at the table” with MKSK as final design pieces of phase two finish up. Additionally, Scott, Murphy and Daniel will assist in gathering cost estimates and schedule planning for construction.
Childers said the challenging nature of phase two’s location made the construction manager format the right choice, since it will occupy land that was at one time a landfill.
“ … This method, we felt like it was the right way,” he said. “They can help us understand where the costs are, what things are really going to look like, how challenging is it to build this idea we have.”
The city will pay $52,445 for pre-construction services and this part is expected to last 90 days. Part two will include the actual construction of phase two of the park, with Scott, Murphy and Daniel overseeing building efforts and bidding out work.
The city will pay $932,219 for this portion, for a total cost of $984,665. By the time construction begins this September, a “guaranteed maximum price” will be put in place on the project. A 4% at-risk fee is also included for Scott, Murphy and Daniel.
Initially, the city planned to cut the ribbon on phase one this summer and then start phase two construction soon thereafter. Childers told the Daily News that as complexities in the project presented themselves, the decision was made to pause.
Work is now expected to start this fall, wrapping up about 12 months later.